System Commissioning Checklists & Acceptance Tests
Learning objectives
- Run a commissioning checklist systematically.
- Define acceptance criteria for each function.
- Verify audio, video, control, and network together.
- Capture sign-off.
Vocabulary
- Commissioning
- On-site testing, tuning, and verification to spec.
- Acceptance test
- A formal test confirming a function meets the criteria.
- Punch list
- Items to fix before final acceptance.
- Sign-off
- Client confirmation the system is accepted.
Lesson content
Commissioning is where the design and code are proven against the spec. A checklist ensures every function is tested, tuned, and accepted — not left to 'it seemed to work.'
Commissioning checklist (by subsystem)
- 1Power: every device powers on; PoE delivering; UPS charged.
- 2Network: every device reachable on its IP; VLANs correct; Dante clocked.
- 3Video: every source displays on every intended output at the right resolution; EDID/handshakes clean.
- 4Audio: every mic heard; AEC verified by test call; no clipping; level comfortable.
- 5Control: every panel button does its action; feedback reflects real state; error states work.
- 6Conferencing: dial/hang; content share; far-end audio both ways; camera presets.
Acceptance criteria
- Write a pass/fail criterion for each function before testing.
- Test from the user's perspective (press the button, look at the result).
- Record results on the checklist; raise a punch list for any fail.
- Get client sign-off once the punch list is closed.
Acceptance is not 'the integrator feels done.' It is the client confirming each criterion passes. A signed checklist protects both sides and defines the start of the warranty period.
Worked example
Commissioning the conference room: power up; ping each device; display laptop on both displays at 1920×1080; speak into each ceiling mic and confirm no echo on a test call; run the Start/Join/Share/Shutdown sequence from the panel; confirm error states by pulling a cable. Every line checked and signed by the client.
Implementation checklist
- ✓Commissioning checklist run per subsystem.
- ✓Acceptance criteria defined and tested.
- ✓Punch list raised and closed.
- ✓Client sign-off captured.
Downloadable study guide
01. Commissioning checklist by subsystem: power, network, video, audio, control, conferencing. 02. Define pass/fail criteria before testing; test from the user's perspective. 03. Raise a punch list; close it; capture client sign-off.