Synthesize the course into a complete design package: interpret a client brief, develop architecture and equipment specs, prepare signal-flow, DSP, network, and control plans, draft commissioning and training, and present and defend the design. This week culminates in the capstone project and the course's final deliverables.

Key Competency

Produce and defend a complete AV design package for a real room.

AV Institute
AV Institute · Week 8Real-World Capstone Project
Lesson

Commissioning Tests, Acceptance Criteria & a User Training Plan

Est. 55 minCompetency: Define how the system will be tested and the user trained.

Learning objectives

  • Write commissioning tests per function.
  • Define acceptance criteria.
  • Plan user training.
  • Tie tests to the requirements.

Lesson content

A design is only done when you can prove it works. Commissioning tests and acceptance criteria tie each function back to a requirement; a training plan ensures the client can actually use it.

Commissioning tests per function

  1. 1For each requirement, write a test and a pass/fail criterion.
  2. 2Test from the user's perspective (press the button, observe the result).
  3. 3Cover edge cases: source missing, display no-response, call drop.
  4. 4Run the test plan and record results; raise a punch list for fails.

Acceptance criteria examples

  • 'Laptop displays at 1920×1080 on both displays within 5 s of selection.'
  • 'Far end reports no echo during a 10-minute test call.'
  • 'Start to ON completes in under 30 s, or shows an error state.'
  • 'Shutdown returns the room to standby with audio muted.'

User training plan

  • Train day-to-day users and an admin/IT backup.
  • Cover Start, source, call, share, volume, Shutdown.
  • Explain error states and support contacts.
  • Leave a quick-start guide and record the training.
Tests tie to requirements

Every test should map to a requirement from the brief. If a function has no test, either it is not required or you have not proven it — both are worth knowing.

Worked example

Test plan: laptop on both displays (pass if both show 1080 within 5 s); test call (pass if far end reports no echo for 10 min); Start sequence (pass if under 30 s or errors cleanly); Shutdown (pass if room at standby, muted). Training: 30 min with users, quick-start guide left, recorded.

Implementation checklist

  • ✓Test per function with pass/fail criteria.
  • ✓Edge cases covered.
  • ✓Each test maps to a requirement.
  • ✓User training plan with a quick-start guide.

Downloadable study guide

study-guide.txtcopy-paste ready
01. Commissioning test per requirement + pass/fail criteria; test from user view.
02. Acceptance criteria are specific and measurable.
03. Train day-to-day users + admin; leave a quick-start guide.